4.6.9 Special Constructions
Certain buildings such as cold stores and swimming pools are subject to particularly stringent requirements for constructions to be vapour-tight. Here, the requirements for both diffusion resistance and airtightness are extra tough.
In cold stores, the Z-value should be at least 500 GPa s m2/kg. The vapour barrier should be placed on the warm side of the insulation (i.e., outside for cold stores and inside for swimming pools).
Penetrations are not recommended and should, in any case, be restricted to those necessary only. It is advisable to bond the vapour barrier to a firm substrate or to place it between two sheets, so that it is well-protected against mechanical impact.
All details should be designed with the utmost care and be subject to strict supervision, as installation defects can have very serious consequences.
4.6.10 Vapour Barriers and Renovation
In renovation work, vapour barriers should be installed in constructions according to the same guidelines applying to similar new constructions. However, it is not to be expected that a vapour barrier installed during renovation will meet the same airtightness requirements applicable to a new build.
Joints between the existing and the new vapour barriers must be airtight. The installation must comply with the guidelines for new constructions, which means that they must be taped, bonded, or caulked joints.
In the case of unutilised loft spaces or sloping walls, the vapour barrier can sometimes be installed between the rafters according to the following steps: Remove the existing insulation and install lengths of vapour barrier between rafters. If there is a risk of damaging the vapour barrier due to projecting nails, etc., a thin layer of rigid insulation can be laid down as a substrate (the thickness of which must be max. one third of the total insulation thickness). Bend the lengths of vapour barrier up along the sides of the rafters and fasten carefully. Make the joint as airtight as possible (e.g., with sealant tape). The joint should be further secured by a wooden strip that will pinch the joint. The remaining insulation is placed on the outside of the vapour barrier.
Plaster ceilings can be considered airtight but can only be retained without a vapour barrier if they are intact (i.e., without cracks or holes, and provided that no changes are made to the construction, including re-insulation) (cf. the box on page 76). When joining a new vapour barrier with an old plaster construction, there should be plenty of overlap between the old construction and the new vapour barrier. The joint should be made tight using tape or sealant tape.
Further information on vapour barriers is available from the Byg-Erfa info sheets on vapour barriers (Byg-Erfa, 2007a; Byg-Erfa, 2008a).
4.7 Moisture Barriers
Moisture barrier is the term used for a layer of material which prevents moisture transport in liquid form. Moisture barriers are commonly used to prevent humidification by soil moisture or discharge of construction-related moisture (e.g., from concrete floors). However, they can also be used for other purposes such as preventing humidification of windows and doors in brickwork.
Moisture barriers are intended to prevent water from ‘wicking’ up (e.g., through a grade construction). When installing moisture barriers, it is important to ensure complete tightness everywhere, so that there will be no moisture infiltration outside the moisture barrier. In foundations, the plaster layer must be interrupted at the level of the bituminous foundation waterproofing (could also be a plastic membrane/wall membrane), as the plaster layer could otherwise act as a wick, drawing moisture up past the moisture barrier.

Figure 44. Example of moisture barrier installed on ground floor slab. The moisture barrier on the deck is sealed tightly with the bituminous foundation waterproofing (which could also be plastic membrane/wall membrane). The bituminous foundation waterproofing is continued on to the deck and bonded or welded to the concrete. The moisture barrier is laid out to overlap with the bituminous foundation waterproofing, which will prevent moisture from wicking up and will act as a radon shield.
Figure 45. The position of a moisture barrier in a wall/foundation and on ground floor slab. The moisture barriers in the wall/foundations are continued to the outside. The moisture barrier is not plastered over as the plaster may act as a ‘wick’ and draw moisture upward. On the inside, the bituminous foundation waterproofing is continued on to the deck and bonded or welded to the concrete. The joint between the wall and deck moisture barriers is sealed tightly with a bonded overlap.
For renovations, a moisture barrier is sometimes used on an existing ground floor slab instead of a capillary break underneath the concrete deck. If this is the case, great care must be taken not to soil the concrete deck, as organic soiling and any humidification occurring when installing the moisture barrier could result in mould growth. The best solution in such cases would be to install a moisture barrier impermeable to oxygen (e.g., a bonded bituminous sheet or a vapour barrier applied in liquid form). The same is true of preventing moisture infiltration after water damage (e.g., resulting from a burst pipe or flooding).
Further information on moisture barriers is available in Fugtspærre i murværk (Moisture Barriers in Brickwork) (Bunch-Nielsen & Christensen, 2002) and in Vejledning om fugtspærre over vinduer og døre i murværk (Guidance to Moisture Barriers Above Windows and Doors in Brickwork) (Danish Technological Institute, 2011).
4.7.1 Radon
Radon is a radioactive soil gas. Radon will primarily enter buildings via leakage paths. This is undesirable because a high radon content in indoor air may increase the risk of lung cancer.
In new builds, moisture control in soil-facing wall and deck constructions will also act as radon shields. In deck constructions, radon entry can be prevented by incorporating a moisture barrier in the floor construction, for example.
In existing buildings, radon entry can normally be reduced by ensuring that ground floor slabs or basement floors are tight, paying special attention to cracks and gaps.
Radon can also be removed via ventilation, as radon will enter the building when air pressure in the building drops (creating positive pressure in the soil relative to the inside of the building). A ventilation solution could be to vent crawl spaces or capillary breaks via vent pipes above roof level.
The best solution is achieved by combining these two measures.
Further information on radon is available from the Byg-Erfa info sheet on radon (Byg-Erfa, 2002).
Figure 46. House ventilation and venting the capillary break via a vent pipe above roof level, combined with radon-proofing, will help to maintain a low indoor-air radon content.
4.8 Wind Barriers
It is sometimes necessary to use windproof flashing on top of the insulation in vented roof constructions or on the outside of the insulation in vented facade constructions. This is to avoid airflow in the insulation material resulting in a reduced thermal insulance factor. Wind barriers can normally be omitted in low buildings where the underlying construction can be regarded as tight. Some insulation materials can withstand a level of wind load without needing a wind barrier. It is important that the windproof layer has a suitably small diffusion resistance compared to that of a vapour barrier (if used), and other layers on the warm side of the windproof roof.
Experience shows that the diffusion resistance of the windproof layer should be 10 times less than the diffusion resistance of the materials on the warm side of the windproof layer. However, buildings with an indoor climate corresponding to humidity exposure class 1 or 2 can (subject to a moisture-performance assessment of the specific construction) sometimes be executed with just a factor-5 difference between the diffusion coefficients.
In addition to the primary performance requirements (which prevent moisture accumulation and air passage in the thermal insulation material) the windproof layer should also meet potential fire performance requirements.
Examples of commonly used wind barriers are shown in Table 5, which also indicates the typical fire classification of the products.
The windproof layer must be durable and, importantly, resistant to the impacts it will be exposed to while in use.
Table 5. Examples of wind barrier materials with a typical Z-value and fire classification. (Note that, for a specific building project, the value applicable to the specific product in question should be used.)
4.9 Fresh-Air Ventilation
A basic measure to prevent moisture damage due to condensation is to ensure a suitably low water vapour content in indoor air via fresh-air ventilation. The necessary air exchange rate is relative to the actual rate of humidification.
The Building Regulations stipulate that, in dwellings, fresh air must be supplied at the rate of at least 0.3 l/s m2, which corresponds to an air exchange rate of at least 0.5 times per hour in a room with a height of 2.5 m.
For rooms in single-family dwellings, the ventilation requirement is considered met by natural ventilation if there is an openable window or opening facing the room as well as an adjustable valve in the window or exterior wall with a free opening totalling at least 60 cm2 per 25 m2 floor area. Furthermore, specific Building Regulations requirements apply to ventilation from bathrooms, toilets, utility rooms, and kitchens. In residential buildings other than single-family dwellings with natural ventilation, mechanical ventilation is a requirement (see Section 3.3.2, Indoor Climate).
4.10 Hydrophobic Coating
Impregnation is performed to reduce humidification of materials, especially in a weather screen.
Applying a coat of proofing compound to the outside the weather screen will achieve a hydrophobic effect in otherwise hydrophilic materials such as brick or concrete.
The materials used for hydrophobic coating should be vapour-permeable to allow water vapour to dissipate.
Hydrophobic coating should be applied with care, as there are both pros and cons associated with its use. Hydrophobic coating will usually only prevent water intrusion in small openings (pores) and cannot effectively close larger openings. This leads to a concentrated water load around large leakages such as cracks in mortar joints. Furthermore, in tall buildings, hydrophobic coating may result in increased water load sustained by the lower parts of the facade because water is no longer absorbed in the upper parts. Hydrophobic coating can also change the look or colour of the treated surface.
Figure 47. Hydrophobic coating.
Water encountering an untreated surface of sorbent material (such as brick), will be wicked evenly and transported into the material in tandem with it being wetted.
If a hydrophobic coating is applied to the surface, moisture will be repelled, and the water will run off instead.
In areas with major leakages or untreated areas, the amount of water being drawn or pressed in by the wind will grow beyond normal levels because run-off from higher areas now add to the water load. Consequently, there is a certain risk of uneven and, in places, more intense humidification.
4.11 Surface Coatings and Treatments
The pore structure of certain materials means that they have good capillary transport properties. When the pores in the material are water-filled, there will be a liquid transport driven by the negative pressure created in the open pores. This quality can be exploited to remove condensate.
Certain calcium silicate sheets and surface treatments (including rendering) possess such qualities.
These materials can be used as interior surface cladding/treatment of damp basement walls.
Here, capillary forces will drive any moisture in the wall to the surface whence it can evaporate. Calcium silicate sheets are available in a version which, besides their capillarity also possess relatively good insulating properties, making them suited to interior re-insulation (breaking thermal bridges) on damp surfaces.
Ordinary rendering on a substrate with a high saline content (such as basement walls exposed to rising damp) will often peel and efflorescence may blemish the surface. In such cases, an option could be to try using special patching compounds, proportioned to contain the efflorescence inside the plaster layer without the plaster dropping off immediately. Patching compound will thus provide a more durable solution than ordinary rendering.
In the case of both rendering and sheeting, please remember that the final surface treatment should be vapour-permeable, like silicate paint.
4.12 Sloping Ground
To reduce water impact, the ground must slope away from the building for the first 3 m. Water is drained off to a gully or dry well.
The slope must be min. 1:40 but can be reduced to 1:50 for surface areas with a permanent compact finish (such as paving slabs). The fact that the ground may settle should be considered when constructing slopes, so that the required gradient will be achieved even after potential settling.
Figure 48. Moisture control measures at a building perimeter:
Sloping ground, min. 1:40 for the first approx. 3 m from the building, and after potential settling. In areas with permanent compact finish, such as paving slabs on patios and walkways, the slope can be reduced to 1:50.
Substructure height of min. 150 mm to avoid humidification in moisture-sensitive lower parts of the exterior wall.
Perimeter drain to remove percolating surface water and avoid water pressure on foundations or basement walls.
4.13 Water Pressure and Drainage
The risk of humidification is especially great if water is allowed to stand along the building perimeter, as this may exert water pressure on the foundations and basement walls and floors. This water pressure will typically come from the surface through the backfill along the outer wall perimeter. It is important, therefore, that the water is drained away as quickly as it enters. This is normally done by placing a perimeter drain along the outside of the foundations. A draining layer, or so-called wall drainage system, is placed along basement walls to intercept surface water, conveying it down to the perimeter drain.
Only where the ground consists of self-draining material (such as coarse sand) can the perimeter drain be omitted. Drainage should be carried out according to DS 436, Code of Practice for the groundwater drainage of structures (Danish Standards, 1993).
For building work carried out in areas where the water table is high, or at great depth below the natural water table, special measures must be implemented to keep out the water.
4.13.1 Drainage Systems
Drainage systems can be subdivided into a filter medium (such as gravel) and a drainage element (drainage run).
The filter medium ensures collection and transport of inflowing water from the surroundings while preventing undesirable transport of solid particles into the medium and further into the drainage run. The filter medium should therefore be made of material with a grain size meeting the so-called filtration criteria, which are rules specifying the relationship between grain sizes in the filter and in the surrounding soil. When designing a filter medium, one should ensure that the size of pores and flow openings gradually increase towards the drainage run.
The drainage run will collect the drainage water and lead it away from the building (normally through a drainage system). Drainage pipes usually have slits or holes in the pipe wall, allowing water to flow into it.a
Drainage runs should be laid with a min. gradient of 3 ‰. Due to frost issues, the lower edge of the foundation for heated buildings should be at least 0.60 m below the level of the finished grade level. Furthermore, the lower edge of the drainage pipe should be at least 0.3 m below the specific structural element (e.g., the basement floor) to be protected against moisture. Excavations must not go deeper than to the lower edge of the substructure. The drainage run should be connected to a min. 300 mm gully with a grit trap and the connection should lie above the highest damming level. Alternatively, the drainage line can terminate in a sump. Here, the water can be pumped into the drainage system (cf. DS 436, Code of Practice for the groundwater drainage of structures (Danish Standards, 1993)). Figure 49 is an example of the positioning of a perimeter drain.

Figure 49. Profile of an exterior concrete basement wall, insulated on the outside, on low and high ground. The upper part of the exterior basement wall is built as an insulated cavity wall. The outside insulation must overlap the insulation in the upper part of the basement wall by at least 200 mm to eliminate thermal bridging, thus reducing energy loss and protecting against surface condensation. This also applies to a high-ground position. On the left side of the figure, the insulation consists of porous insulation while, on the right, polystyrene insulation with drainage grooves on the outside has been used. To protect against water pressure to the exterior basement wall, a perimeter drain has been installed to drain away percolating water. Transfer pipes drain water from the capillary break beneath the concrete floor to the perimeter drain. The ground slopes away from the building.
Pipe dimensions should be min. 70 mm to allow cleaning. Pipes and fittings should meet the requirements of DS 436, Code of Practice for the groundwater drainage of structures (Danish Standards, 1993). Pipes without sleeves should not be used.
To avoid the risk of blockage, the drainage pipe must be enclosed by a filter medium. This filter could be geotextile fabric whose permeability should be adjusted to the specific soil type. The pores in the geotextile fabric should be sufficiently large to ensure that the fabric will not clog.
The filter could also consist of course sand/gravel. If the surrounding soil consists of clay (solid cohesive soil). The filter medium could be a layer of coated, expanded clay aggregate pellets, small pebbles (2–8 mm), pea gravel (5–16 mm), or coarser materials, along with 80 mm perforated plastic piping, or similar. In sand and similar (non-cohesive soil), a filter medium of well-graded sand with d10 > 0.3 mm and 1.5 mm < d50 < 2.5 mm would be suitable. In this case, the slits in the drainpipes must be max. 1.5 mm wide.